Bitola–Prilep highway: 28 kilometres to be asphalted by end of 2028
The Municipality of Bitola says 12 km will open in 2027; the stretch toward Prilep will be completed last because of expropriation and utility relocations.

The Municipality of Bitola says that by the end of 2028 a total of 28 kilometres of the Bitola–Prilep highway will be asphalted, and that 12 kilometres of that will be opened to traffic next year.
The announcement followed a meeting between Bitola Mayor Toni Konjanovski and representatives of Bechtel and Enka about progress on the project.
Schedule and remaining challenges
According to the municipality, "One section 12 kilometres long will be opened to traffic in 2027, when work will also be carried out on the section in front of Bitola, so that by the end of 2028 a total of 28 kilometres of motorway will be asphalted. The section towards Prilep will be put into operation last, because certain issues with expropriation and the relocation of existing infrastructure must first be resolved," the Municipality of Bitola said.
The statement clarifies that the 12-kilometre stretch to be opened in 2027 is part of a phased rollout: work on the portion immediately before Bitola will proceed in parallel so the 28-kilometre figure is reached by the end of 2028.
Earlier plans foresee construction covering 40 kilometres in total; the whole route is scheduled for completion by 2029.
Municipal officials emphasised that resolving land-expropriation claims and relocating utilities and other infrastructure on the Prilep side are prerequisites before that section can be commissioned.