Construction of a wastewater network in the Kumanovo villages of Tabanovce and Sopot remains incomplete despite €800,000 having been spent, residents say, because parts of the route are blocked by unresolved property and legal disputes.

Angry villagers asked the Municipality of Kumanovo for answers at the council’s most recent session, demanding to know why the works are stalled and what steps will be taken to finish the system that is currently non‑functional.

What the municipality says

"The project started according to the planned schedule, but due to unresolved property-legal relations construction stopped in one section, and continued on sections where expropriation had been carried out. The funds have been fully used, the project is closed, and the wastewater sewer has not been put into use," answered Lidija Lang-Spasovska, head of the Communal Affairs Sector at the Municipality of Kumanovo.

According to municipal records, in 2021 the Municipality of Kumanovo received 47.7 million denars (800,000 euros) from the Government for construction of a sewage system with a main collector and a secondary network in the border villages of Tabanovce, Chetirce and Sopot. The scheme was supposed to connect to the sewer system in the village of Dolno Konjare.

The funds were provided through the Ministry of Transport and Communications as part of the TAV project, following the abandonment of plans to build a cargo airport in Shtip. The contractor on the works was the company Zikol, and construction began in December 2021.

Residents and some councillors say sections of newly laid infrastructure now have no use because they cannot be connected along the disputed stretches; they are pressing the municipality for a concrete timeline and legal steps to resolve expropriation and land-right issues so the system can be completed and commissioned.