Treska site in central Skopje: 11 buildings approved, access routed through narrow Vladimir Poležanovski and Ruzveltova streets

Large-scale residential construction is underway on the site of the former Treska factory in central Skopje: developers have begun erecting multiple "Napolitanka"-style apartment blocks, some facades are already being finished and units are being marketed as a luxury complex. The project does not include a kindergarten.

Centar Municipality says it has issued 11 final building permits for the site. The approvals were signed during the administration of Mayor Goran Gerasimovski.

When asked how vehicles will enter and leave the new complex, the mayor's office referred to the Detailed Urban Plan. "The traffic solution for the entry and exit of the new residents, as well as the construction of new streets within the 'Treska' complex, are foreseen in accordance with the valid Detailed Urban Plan," Centar Municipality told us.

Access through narrow streets, an exit to Teodosij Gologanov blocked by police

Under the current Detailed Urban Plan, access is planned via Vladimir Poležanovski Street, a narrow road where two cars barely pass. The plan also foresees extending Borka Taleski Street across the complex so it would continue to Ruzveltova Street — increasing traffic within the neighbourhood.

Centar Municipality sought permission to cut a new street that would lead out to Teodosij Gologanov Boulevard and obtained consent from the City of Skopje, but the Ministry of Interior refused that traffic solution and denied an exit onto the boulevard.

Construction of the first building started in 2023, during Gerasimovski's first term as mayor, marking a rapid conversion of the last open plot in central Skopje into apartment blocks. Critics note the current development departs from an earlier design process: in 2017, then-mayor Sasa Bogdanovic and the Association of Architects launched a public competition that produced three concept proposals, all of which included semi-open building layouts, a kindergarten and green space.

When Gerasimovski ran for mayor in 2021 he annulled that competition declaring it unlawful and argued landowners could reshape parcels and seek building permits. Shortly afterwards, state parcels began to be sold and companies including Golden Art and Mega i Akustik reorganised plots to obtain permits. Opponents say construction continues around the clock and that municipal decisions favour building firms over public interest.

Photo: SDK.MK)

Related articles